Sno. |
EVENT |
TIME LIMIT |
|
|
in months from '0' date |
|
|
|
1 |
Allocation |
0 |
|
|
|
2 |
Purchase of GR |
1.5 |
|
|
|
|
|
|
3 |
Bank Guarantee |
3 |
|
|
|
|
|
|
4 |
Mining Lease Application |
3 |
|
|
|
5 |
Mining Plan submission |
6 |
|
|
|
6 |
Mining Plan approval |
8 |
|
|
|
7 |
Previous approval application |
11 |
|
|
|
8 |
Previous approval |
11 |
|
|
|
9 |
Forest Clearance application |
12 |
|
|
|
10 |
Forest Clearance |
18 |
|
|
|
11 |
Environment Clearance |
12 |
|
Application |
|
|
|
|
12 |
Environment Clearance |
18 |
|
|
|
13 |
Mining Lease grant |
24 |
|
|
|
14 |
Land acquisition begin |
9, 19 |
|
|
|
15 |
Land Acquisition |
30, 36 |
|
|
|
16 |
Opening permission application |
34, 40 for OC |
|
|
46, 52 for UG |
|
|
|
17 |
Opening permission grant |
35, 41 for OC |
|
|
4753 for UG |
|
|
|
18 |
Production |
36, 42 for OC |
|
|
48, 54 for UG |
|
|
|
19 |
Reaching Rated Capacity |
|